Saffin, T. and Laryea, S. (2012) The use of risk registers by project managers. In: 4th West Africa Built Environment Research (WABER) Conference, 24-26 July 2012, Abuja, Nigeria, pp. 1305-1318.

[img]
Preview
Text - Published Version
· Please see our End User Agreement before downloading.

561kB

It is advisable to refer to the publisher's version if you intend to cite from this work. See Guidance on citing.

Official URL: http://waberconference.com/index.php?option=com_ph...

Abstract/Summary

The construction industry is widely recognised as being inherent with risk and uncertainty. This necessitates the need for effective project risk management to achieve the project objectives of time, cost and quality. A popular tool employed in projects to aid in the management of risk is a risk register. This tool documents the project risks and is often employed by the Project Manager (PM) to manage the associated risks on a project. This research aims to ascertain how widely risk registers are used by Project Managers as part of their risk management practices. To achieve this aim entailed interviewing ten PMs, to discuss their use of the risk register as a risk management tool. The results from these interviews indicated the prevalent use of this document and recognised its effectiveness in the management of project risks. The findings identified the front end and feasibility phases of a project as crucial stages for using risk registers, noting it as a vital ingredient in the risk response planning of the decision making process. Moreover, the composition of the risk register was also understood, with an insight into how PMs produce and develop this tool also ascertained. In conclusion, this research signifies the extensive use of the risk register by PMs. A majority of PMs were of the view that risk registers constitute an essential component of their project risk management practices. This suggests a need for further research on the extent to which risk registers actually help PMs to control the risks in a construction project, particularly residual risks, and how this can be improved to minimize deviations from expected outcomes.

Item Type:Conference or Workshop Item (Paper)
Refereed:Yes
Divisions:Science > School of the Built Environment
ID Code:30322
Uncontrolled Keywords:interview, project manager, risk management, risk register, UK
Additional Information:In: Laryea, S., Agyepong, S.A., Leiringer, R. and Hughes, W. (Eds) Procs 4th West Africa Built Environment Research (WABER) Conference