Duration and cost variability of construction activities: an empirical study

Ballesteros-Pérez, P., Sanz-Ablanedo, E., Soetanto, R., González-Cruz, M.C., Larsen, G. and Cerezo-Narváez, A. (2020) Duration and cost variability of construction activities: an empirical study. Engineering Construction and Architectural Management, 146 (1). ISSN 1365-232x

[img]
Preview
Text - Accepted Version
· Please see our End User Agreement before downloading.

978kB

It is advisable to refer to the publisher's version if you intend to cite from this work. See Guidance on citing.

To link to this item DOI: 10.1061/(ASCE)CO.1943-7862.0001739

Abstract/Summary

The unique nature of construction projects can mean that construction activities often suffer from duration and cost variability. Because this variability is unplanned, it can present a problem when attempting to complete a project on time and on budget. Various factors causing this variability have been identified in the literature, but they predominantly refer to the nature and/or context of the whole project rather than specific activities. In this paper, the order of magnitude of and correlation between activity duration and cost variability is analyzed in 101 construction projects with over 5,000 activities. To do this, the first four moments (mean, standard deviation, skewness, and kurtosis) of actual versus planned duration and cost (log) ratios are analyzed by project, phase of execution, and activity type. Results suggest that, contrary to common wisdom, construction activities do not end late on average. Instead, the large variability in the activity duration is the major factor causing significant project delays and cost overruns. The values of average activity duration and cost variability gathered in this study will also serve as a reference for construction managers to improve future construction planning and project simulation studies with more realistic data.

Item Type:Article
Refereed:Yes
Divisions:Science > School of the Built Environment > Organisation, People and Technology group
ID Code:85395
Publisher:Wiley Blackwell

Downloads

Downloads per month over past year

University Staff: Request a correction | Centaur Editors: Update this record

Page navigation